Renewable sites › M Sport, Dovenby Hall Estate - Solar Panels
M Sport, Dovenby Hall Estate - Solar Panels
M Sport, Dovenby Hall Estate - Solar Panels is operational in Cumberland with a recorded capacity of 0.8 MW, and has been generating since 2023-10-01.
Planning and build timeline
| Application submitted | 2023-01-24 |
| Permission granted | 2023-02-13 1 months after submission |
| Operational | 2023-10-01 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cumberland’s record on solar
Cumberland has decided 28 solar farms and approved 93%, taking a median of 2.9 months. See every solar farm decision in Cumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tallentire Hill Wind Onshore · Operational | 12 | 1.8 km |
Arkleby Mill Anaerobic Digestion · Operational | 1 | 6.2 km |
Aspatria Creamery Anaerobic Digestion · Operational | 5 | 6.9 km |
Wharrels Hill Wind Farm Wind Onshore · Operational | 10.4 | 7.5 km |
Land at Flimby Hall Farm Wind Onshore · Operational | 6.2 | 8.4 km |
Westnewton Wind Onshore · Operational | 6.2 | 8.7 km |
Aspatria Solar Photovoltaics · Operational | 19 | 9.1 km |
Wythegill Wind Turbine Wind Onshore · Operational | 2.3 | 9.4 km |
How big is M Sport, Dovenby Hall Estate - Solar Panels?
M Sport, Dovenby Hall Estate - Solar Panels has a recorded installed capacity of 0.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates M Sport, Dovenby Hall Estate - Solar Panels?
REPD records the operator as M-Sport Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was M Sport, Dovenby Hall Estate - Solar Panels approved and built?
The application was submitted on 2023-01-24. Permission was granted on 2023-02-13, 1 months later. The site became operational on 2023-10-01, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 13131.