Congresbury Solar Farm is operational in North Somerset with a recorded capacity of 7.1 MW, and has been generating since 2015-12-19.

7.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-19
Solar Photovoltaics
Technology
FIM Solar Distribution
North Somerset
Authority
England

Planning and build timeline

Application submitted2014-06-19
Permission granted2014-11-20
5 months after submission
Operational2015-12-19
13 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Somerset’s record on solar

North Somerset has decided 39 solar farms and approved 95%, taking a median of 2.9 months. See every solar farm decision in North Somerset

Other built sites within 15 km

SiteMWDistance
Twin Elm Solar Farm
Solar Photovoltaics · Operational
12.2 km
Bowerhouse Farm (extension)
Solar Photovoltaics · Under Construction
19.82.4 km
Iwood Lane Solar Farm
Solar Photovoltaics · Operational
82.5 km
Bowerhouse Farm
Solar Photovoltaics · Operational
8.32.6 km
Towerbrook Farm (Banwell Solar Farm)
Solar Photovoltaics · Operational
7.22.9 km
The Grange
Solar Photovoltaics · Operational
84.3 km
Arnolds Way, Yatton - Solar Panels
Solar Photovoltaics · Under Construction
0.844.6 km
Smart Systems Limited, Arnolds Way - Solar Panels
Solar Photovoltaics · Under Construction
2.934.8 km

How big is Congresbury Solar Farm?

Congresbury Solar Farm has a recorded installed capacity of 7.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Congresbury Solar Farm?

REPD records the operator as FIM Solar Distribution. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Congresbury Solar Farm approved and built?

The application was submitted on 2014-06-19. Permission was granted on 2014-11-20, 5 months later. The site became operational on 2015-12-19, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1952.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council