May Farm Anaerobic Digester (Farm AD) is operational in East Cambridgeshire with a recorded capacity of 2.4 MW, and has been generating since 2013-12-12.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-12-12
Anaerobic Digestion
Technology
Barway Farms /Shropshire Energy
East Cambridgeshire
Authority
England

Planning and build timeline

Application submitted2011-06-09
Permission granted2012-11-29
18 months after submission
Operational2013-12-12
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Toggam Farm
Solar Photovoltaics · Operational
12.510.4 km
Toggam Farm - Anaerobic Digestion Plant
Anaerobic Digestion · Operational
110.8 km
Willow Farm
Solar Photovoltaics · Operational
1.1511.3 km
Colony Farm
Anaerobic Digestion · Under Construction
411.7 km
Triangle Solar Farm Park
Solar Photovoltaics · Operational
1214.2 km
North Angle Farm
Solar Photovoltaics · Under Construction
29.414.9 km

How big is May Farm Anaerobic Digester (Farm AD)?

May Farm Anaerobic Digester (Farm AD) has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates May Farm Anaerobic Digester (Farm AD)?

REPD records the operator as Barway Farms /Shropshire Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was May Farm Anaerobic Digester (Farm AD) approved and built?

The application was submitted on 2011-06-09. Permission was granted on 2012-11-29, 18 months later. The site became operational on 2013-12-12, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 273.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council