Renewable sites › The Stables
The Stables
The Stables is an operational 1.8 MW solar farm in Hinckley and Bosworth, generating since 22 August 2014. Planning permission was granted on 14 April 2014, 17 months after submission. Operator of record: Anesco.
Planning and build timeline
| Application submitted | 29 October 2012 |
| Permission granted | 14 April 2014 17 months after submission |
| Operational | 22 August 2014 4 months after consent |
Screening a site of your own?
Hinckley and Bosworth approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with The Stables’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Hinckley and Bosworth’s record on solar
Hinckley and Bosworth has decided 25 solar farms and approved 96%, taking a median of 3 months. See every solar farm decision in Hinckley and Bosworth →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 1.9 km |
Landfill Gas · Operational | 1.2 | 7.1 km |
Solar Photovoltaics · Operational | 3.5 | 7.1 km |
Landfill Gas · Operational | 2.7 | 7.1 km |
Solar Photovoltaics · Operational | 5 | 7.2 km |
Wind Onshore · Operational | 1.6 | 8.9 km |
Solar Photovoltaics · Operational | 5 | 9.8 km |
Solar Photovoltaics · Operational | 6 | 10 km |
How big is The Stables?
The Stables has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates The Stables?
REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was The Stables approved and built?
The application was submitted on 29 October 2012. Permission was granted on 14 April 2014, 17 months later. The site became operational on 22 August 2014, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1510.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode