Renewable sitesStoke Bardolph energy crop (Farm AD)

Stoke Bardolph energy crop (Farm AD)

Stoke Bardolph energy crop (Farm AD) is operational in Gedling with a recorded capacity of 2 MW, and has been generating since 2010-07-10.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-07-10
Anaerobic Digestion
Technology
Severn Trent Water
Gedling
Authority
England

Planning and build timeline

Application submitted2009-02-18
Permission granted2009-03-11
1 months after submission
Operational2010-07-10
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Severn Trent Water - Stoke Bardolph Wind Turbine
Wind Onshore · Operational
1.50.3 km
Colwick Industrial Estate (Farm and Food waste)
Anaerobic Digestion · Operational
22.9 km
Gedling Solar Farm
Solar Photovoltaics · Operational
5.73.3 km
Radcliffe Solar Farm
Solar Photovoltaics · Operational
4.24.7 km
Stragglethorpe Road farm
Solar Photovoltaics · Operational
55.6 km
Cotgrave solar farm
Solar Photovoltaics · Operational
4.96.5 km
Trent Basin Community Battery
Battery · Operational
0.56.7 km
Dorket Head
Landfill Gas · Operational
2.87.1 km

How big is Stoke Bardolph energy crop (Farm AD)?

Stoke Bardolph energy crop (Farm AD) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stoke Bardolph energy crop (Farm AD)?

REPD records the operator as Severn Trent Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stoke Bardolph energy crop (Farm AD) approved and built?

The application was submitted on 2009-02-18. Permission was granted on 2009-03-11, 1 months later. The site became operational on 2010-07-10, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 213.