Renewable sites › Trent Basin Community Battery
Trent Basin Community Battery
Trent Basin Community Battery is operational in Nottingham with a recorded capacity of 0.5 MW, and has been generating since 2018-07-15.
Planning and build timeline
| Application submitted | 2016-12-21 |
| Permission granted | not recorded |
| Operational | 2018-07-15 |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Eastcroft Municipal Depot Solar Photovoltaics · Operational | 0.18 | 0.9 km |
Eastcroft Municipal Depot Battery · Operational | 0.6 | 0.9 km |
Eastcroft EfW (Lines 1 & 2) EfW Incineration · Operational | 9 | 0.9 km |
Willow Road - Roof mounted solar panels Solar Photovoltaics · Operational | 0.35 | 3.6 km |
Radcliffe Solar Farm Solar Photovoltaics · Operational | 4.2 | 4.4 km |
Colwick Industrial Estate (Farm and Food waste) Anaerobic Digestion · Operational | 2 | 4.5 km |
Stragglethorpe Road farm Solar Photovoltaics · Operational | 5 | 5.2 km |
Cotgrave solar farm Solar Photovoltaics · Operational | 4.9 | 5.7 km |
How big is Trent Basin Community Battery?
Trent Basin Community Battery has a recorded installed capacity of 0.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Trent Basin Community Battery?
REPD records the operator as EvoEnergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Trent Basin Community Battery approved and built?
The application was submitted on 2016-12-21. REPD does not record a grant date. The site became operational on 2018-07-15.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6993.