Renewable sites › Mackies Dairy PV
Mackies Dairy PV
Mackies Dairy PV is operational in Aberdeenshire with a recorded capacity of 1.8 MW, and has been generating since 2015-09-28.
Planning and build timeline
| Application submitted | 2014-02-11 |
| Permission granted | 2014-05-12 3 months after submission |
| Operational | 2015-09-28 17 months after consent |
Aberdeenshire’s record on solar
Aberdeenshire has decided 39 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hill of Easterton Wind Onshore · Operational | 2.5 | 0.3 km |
Hill of Easterton Extension Wind Onshore · Operational | 2 | 0.3 km |
Denhill Wind Onshore · Operational | 2.3 | 4.7 km |
St Johns Wells Wind Cluster Extension Wind Onshore · Operational | 3.2 | 5.5 km |
St John's Well Wind Onshore · Operational | 2.4 | 6.6 km |
Haddo Wind Onshore · Operational | 4.6 | 7.5 km |
Courtstone Wind Turbine Wind Onshore · Operational | 2.3 | 7.9 km |
Overhill Farm, Rothienorman - Battery Energy Storage Battery · Under Construction | 49.9 | 8.5 km |
How big is Mackies Dairy PV?
Mackies Dairy PV has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mackies Dairy PV?
REPD records the operator as Mackies Of Scotland Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mackies Dairy PV approved and built?
The application was submitted on 2014-02-11. Permission was granted on 2014-05-12, 3 months later. The site became operational on 2015-09-28, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1501.