Novarly ParcelRenewable sites

Renewable sitesShantavny Scotch

Shantavny Scotch

Shantavny Scotch is operational in Mid Ulster with a recorded capacity of 16.1 MW, and has been generating since 2017-03-16.

16.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-16
Wind Onshore
Technology
Tyrone Wind Energy Ltd
Mid Ulster
Authority
Northern Ireland

Planning and build timeline

Application submitted2007-10-29
Permission granted2012-02-24
52 months after submission
Operational2017-03-16
61 months after consent

Mid Ulster’s record on onshore wind

Mid Ulster has decided 27 onshore wind schemes and approved 85%, taking a median of 21 months. See every onshore wind scheme decision in Mid Ulster

Other built sites within 15 km

SiteMWDistance
Slieve Divena Phase 1 Wind Farm
Wind Onshore · Operational
303.7 km
Slieve Divena Phase 2 Wind Farm
Wind Onshore · Operational
18.83.7 km
Altamuskin Extension
Wind Onshore · Operational
7.14.3 km
Altamuskin
Wind Onshore · Operational
7.15.1 km
Gortfinbar
Wind Onshore · Operational
158.8 km
Crockbaravally Wind Farm
Wind Onshore · Operational
7.58.9 km
Crockagarran
Wind Onshore · Operational
159.5 km
Crockagarron Ext
Wind Onshore · Operational
2.59.9 km

How big is Shantavny Scotch?

Shantavny Scotch has a recorded installed capacity of 16.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Shantavny Scotch?

REPD records the operator as Tyrone Wind Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Shantavny Scotch approved and built?

The application was submitted on 2007-10-29. Permission was granted on 2012-02-24, 52 months later. The site became operational on 2017-03-16, 61 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4325.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council