Shantavny Scotch
Shantavny Scotch is an operational 16.1 MW onshore wind farm in Mid Ulster, generating since 16 March 2017. Planning permission was granted on 24 February 2012, 52 months after submission. Operator of record: Tyrone Wind Energy Ltd.
Planning and build timeline
| Application submitted | 29 October 2007 |
| Permission granted | 24 February 2012 52 months after submission |
| Operational | 16 March 2017 61 months after consent |
Screening a site of your own?
Mid Ulster approves 85% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Shantavny Scotch’s recorded coordinate — swap in your own postcode or coordinates.
Mid Ulster’s record on onshore wind
Mid Ulster has decided 27 onshore wind schemes and approved 85%, taking a median of 21 months. See every onshore wind scheme decision in Mid Ulster →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 30 | 3.7 km |
Wind Onshore · Operational | 18.8 | 3.7 km |
Wind Onshore · Operational | 7.1 | 4.3 km |
Wind Onshore · Operational | 7.1 | 5.1 km |
Wind Onshore · Operational | 15 | 8.8 km |
Wind Onshore · Operational | 7.5 | 8.9 km |
Wind Onshore · Operational | 15 | 9.5 km |
Wind Onshore · Operational | 2.5 | 9.9 km |
How big is Shantavny Scotch?
Shantavny Scotch has a recorded installed capacity of 16.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Shantavny Scotch?
REPD records the operator as Tyrone Wind Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Shantavny Scotch approved and built?
The application was submitted on 29 October 2007. Permission was granted on 24 February 2012, 52 months later. The site became operational on 16 March 2017, 61 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4325.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode