Renewable sites › Shantavny Scotch
Shantavny Scotch
Shantavny Scotch is operational in Mid Ulster with a recorded capacity of 16.1 MW, and has been generating since 2017-03-16.
Planning and build timeline
| Application submitted | 2007-10-29 |
| Permission granted | 2012-02-24 52 months after submission |
| Operational | 2017-03-16 61 months after consent |
Mid Ulster’s record on onshore wind
Mid Ulster has decided 27 onshore wind schemes and approved 85%, taking a median of 21 months. See every onshore wind scheme decision in Mid Ulster →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Slieve Divena Phase 1 Wind Farm Wind Onshore · Operational | 30 | 3.7 km |
Slieve Divena Phase 2 Wind Farm Wind Onshore · Operational | 18.8 | 3.7 km |
Altamuskin Extension Wind Onshore · Operational | 7.1 | 4.3 km |
Altamuskin Wind Onshore · Operational | 7.1 | 5.1 km |
Gortfinbar Wind Onshore · Operational | 15 | 8.8 km |
Crockbaravally Wind Farm Wind Onshore · Operational | 7.5 | 8.9 km |
Crockagarran Wind Onshore · Operational | 15 | 9.5 km |
Crockagarron Ext Wind Onshore · Operational | 2.5 | 9.9 km |
How big is Shantavny Scotch?
Shantavny Scotch has a recorded installed capacity of 16.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Shantavny Scotch?
REPD records the operator as Tyrone Wind Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Shantavny Scotch approved and built?
The application was submitted on 2007-10-29. Permission was granted on 2012-02-24, 52 months later. The site became operational on 2017-03-16, 61 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4325.
Novarly Parcel · official public data, read properly · parcel.novarly.com