Renewable sites › Crockagarron Ext
Crockagarron Ext
Crockagarron Ext is operational in Fermanagh and Omagh with a recorded capacity of 2.5 MW, and has been generating since 2012-06-01.
Planning and build timeline
| Application submitted | 2009-03-04 |
| Permission granted | 2010-12-08 21 months after submission |
| Operational | 2012-06-01 18 months after consent |
Fermanagh and Omagh’s record on onshore wind
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crockagarran Wind Onshore · Operational | 15 | 0.5 km |
Gortfinbar Wind Onshore · Operational | 15 | 1.1 km |
Inishative Wind Onshore · Operational | 13.8 | 1.7 km |
Crockbaravally Wind Farm Wind Onshore · Operational | 7.5 | 2.5 km |
Crockdun Wind Onshore · Operational | 12.5 | 3.2 km |
Eshmore Wind Onshore · Operational | 6.9 | 4.3 km |
Altamuskin Wind Onshore · Operational | 7.1 | 6.4 km |
Crockbrack Wind Onshore · Operational | 2 | 7.8 km |
How big is Crockagarron Ext?
Crockagarron Ext has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Crockagarron Ext?
REPD records the operator as Northern Wind Power�. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Crockagarron Ext approved and built?
The application was submitted on 2009-03-04. Permission was granted on 2010-12-08, 21 months later. The site became operational on 2012-06-01, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3717.
Novarly Parcel · official public data, read properly · parcel.novarly.com