Novarly ParcelRenewable sites

Renewable sitesScroby Sands�

Scroby Sands�

Scroby Sands� is operational in DECC (S36) with a recorded capacity of 60 MW, and has been generating since 2004-03-01.

60 MW
Capacity
as recorded in REPD
Operational
Status
since 2004-03-01
Wind Offshore
Technology
E.ON UK
DECC (S36)
Authority
England

Planning and build timeline

Application submitted2001-03-05
Permission granted2002-12-01
21 months after submission
Operational2004-03-01
15 months after consent

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Nova Scotia Farm solar park
Solar Photovoltaics · Operational
13.96.3 km
James Paget University Hospital - Design And Installation Of PV Panels
Solar Photovoltaics · Under Construction
10.3 km
Bloodhills - repowering
Wind Onshore · Operational
111 km
South Beach Wind Turbine (Somerton)
Wind Onshore · Operational
1.511.7 km

How big is Scroby Sands�?

Scroby Sands� has a recorded installed capacity of 60 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Scroby Sands�?

REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Scroby Sands� approved and built?

The application was submitted on 2001-03-05. Permission was granted on 2002-12-01, 21 months later. The site became operational on 2004-03-01, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2498.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council