Renewable sitesBloodhills - repowering

Bloodhills - repowering

Bloodhills - repowering is an operational 1 MW onshore wind farm in Great Yarmouth, generating since 15 June 2015. Planning permission was granted on 14 May 2013, 3 months after submission. Operator of record: The Farm Energy Partnership LLP.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 15 June 2015
Wind Onshore
Technology
The Farm Energy Partnership LLP
Great Yarmouth
Authority
England

Planning and build timeline

Application submitted12 February 2013
Permission granted14 May 2013
3 months after submission
Operational15 June 2015
25 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Great Yarmouth: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bloodhills - repowering’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
1.50.7 km
Solar Photovoltaics · Operational
13.95.6 km
Wind Offshore · Operational
6011 km

How big is Bloodhills - repowering?

Bloodhills - repowering has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bloodhills - repowering?

REPD records the operator as The Farm Energy Partnership LLP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bloodhills - repowering approved and built?

The application was submitted on 12 February 2013. Permission was granted on 14 May 2013, 3 months later. The site became operational on 15 June 2015, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3924.