Salford Refuse Treatment Plant (AD) is an operational 2 MW anaerobic digestion plant in Salford, generating since 30 November 2013. Planning permission was granted on 6 March 2008, 7 months after submission. Operator of record: Viridor.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 30 November 2013
Anaerobic Digestion
Technology
Viridor
Salford
Authority
England

Planning and build timeline

Application submitted15 August 2007
Permission granted6 March 2008
7 months after submission
Operational30 November 2013
69 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Salford: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Salford Refuse Treatment Plant (AD)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
0.482.3 km
Landfill Gas · Operational
13.4 km
Solar Photovoltaics · Under Construction
0.174.5 km
Battery · Under Construction
105.4 km
Solar Photovoltaics · Operational
0.155.7 km
EfW Incineration · Operational
33.55.8 km
Solar Photovoltaics · Under Construction
3.386.4 km
Solar Photovoltaics · Operational
0.76.4 km

How big is Salford Refuse Treatment Plant (AD)?

Salford Refuse Treatment Plant (AD) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Salford Refuse Treatment Plant (AD)?

REPD records the operator as Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Salford Refuse Treatment Plant (AD) approved and built?

The application was submitted on 15 August 2007. Permission was granted on 6 March 2008, 7 months later. The site became operational on 30 November 2013, 69 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 912.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode