Novarly ParcelRenewable sites

Renewable sitesRiver Coiltie Hydro Scheme

River Coiltie Hydro Scheme

River Coiltie Hydro Scheme is an operational 1.9 MW hydro scheme in Highland, generating since 1 July 2017. Planning permission was granted on 18 September 2015, 2 months after submission. Operator of record: Green Highland Renewables.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2017
Small Hydro
Technology
Green Highland Renewables
Highland
Authority
Scotland

Planning and build timeline

Application submitted7 July 2015
Permission granted18 September 2015
2 months after submission
Operational1 July 2017
21 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with River Coiltie Hydro Scheme’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
45.1 km
Pumped Storage Hydroelectricity · Operational
3007 km
Large Hydro · Operational
5.27.9 km
Wind Onshore · Operational
11011.8 km
Small Hydro · Operational
312 km
Large Hydro · Operational
1513.8 km
Small Hydro · Operational
214.6 km

How big is River Coiltie Hydro Scheme?

River Coiltie Hydro Scheme has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates River Coiltie Hydro Scheme?

REPD records the operator as Green Highland Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was River Coiltie Hydro Scheme approved and built?

The application was submitted on 7 July 2015. Permission was granted on 18 September 2015, 2 months later. The site became operational on 1 July 2017, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5418.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode