Minster Abbey, Bedlam Court Lane - Solar PV panels is under construction in Thanet with a recorded capacity of 33 MW.
Planning and build timeline
| Application submitted | 2021-09-09 |
| Permission granted | not recorded |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
- Conservation area — Minster Conservation Area
- Scheduled monument — Monastic grange and pre-Conquest nunnery at Minster Abbey
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Thanet’s record on solar
Thanet has decided 20 solar farms and approved 95%, taking a median of 2.3 months. See every solar farm decision in Thanet →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Thorne Farm Solar Photovoltaics · Operational | 6.2 | 2.2 km |
Ebbsfleet Farm Solar Farm Solar Photovoltaics · Operational | 4.9 | 2.6 km |
Ebbsfleet Solar Farm Solar Photovoltaics · Operational | 5 | 2.7 km |
Richborough Energy Park Battery · Operational | 49.9 | 2.8 km |
Richborough Energy Park - Phase 2 Battery · Operational | 50.1 | 2.8 km |
Richborough Energy Park - Phase 3 (Sheaf) Battery · Under Construction | 249 | 3 km |
Harrington Franklin, Richborough Energy Park - Battery Storage Battery · Under Construction | 49.9 | 3.5 km |
Manston Solar Farm Solar Photovoltaics · Operational | 9.9 | 4.2 km |
How big is Minster Abbey, Bedlam Court Lane - Solar PV panels?
Minster Abbey, Bedlam Court Lane - Solar PV panels has a recorded installed capacity of 33 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Minster Abbey, Bedlam Court Lane - Solar PV panels?
REPD records the operator as The Benedictine Nuns of St Mildreds Priory. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Minster Abbey, Bedlam Court Lane - Solar PV panels approved and built?
The application was submitted on 2021-09-09. REPD does not record a grant date. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9681.
Novarly Parcel · official public data, read properly · parcel.novarly.com