Rhosygilwen Solar Farm is operational in Pembrokeshire with a recorded capacity of 1 MW, and has been generating since 2011-07-09.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-07-09
Solar Photovoltaics
Technology
Private Developer
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted2010-11-23
Permission granted2011-01-06
1 months after submission
Operational2011-07-09
6 months after consent

Pembrokeshire’s record on solar

Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Crugmore Farm
Solar Photovoltaics · Operational
6.46.3 km
Llwyn Du Solar Farm
Solar Photovoltaics · Operational
810.5 km
Aberporth Solar Farm
Solar Photovoltaics · Operational
1.510.6 km
Blaen Bowi Wind Farm
Wind Onshore · Operational
3.913.1 km
Dyffryn Brodyn Wind Farm
Wind Onshore · Operational
5.514 km

How big is Rhosygilwen Solar Farm?

Rhosygilwen Solar Farm has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Rhosygilwen Solar Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Rhosygilwen Solar Farm approved and built?

The application was submitted on 2010-11-23. Permission was granted on 2011-01-06, 1 months later. The site became operational on 2011-07-09, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1055.