Blaen Bowi Wind Farm
Blaen Bowi Wind Farm is an operational 3.9 MW onshore wind farm in Carmarthenshire, generating since 30 July 2002. Planning permission was granted on 4 January 2001, 6 months after submission. Operator of record: WINDJEN POWER LTD.
Planning and build timeline
| Application submitted | 27 June 2000 |
| Permission granted | 4 January 2001 6 months after submission |
| Operational | 30 July 2002 19 months after consent |
Screening a site of your own?
Carmarthenshire approves 70% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Blaen Bowi Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Carmarthenshire’s record on onshore wind
Carmarthenshire has decided 10 onshore wind schemes and approved 70%, taking a median of 11.7 months. See every onshore wind scheme decision in Carmarthenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1 | 13.1 km |
Solar Photovoltaics · Operational | 8 | 13.6 km |
Wind Onshore · Operational | 5.5 | 14 km |
Wind Onshore · Operational | 23 | 14.1 km |
How big is Blaen Bowi Wind Farm?
Blaen Bowi Wind Farm has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Blaen Bowi Wind Farm?
REPD records the operator as WINDJEN POWER LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Blaen Bowi Wind Farm approved and built?
The application was submitted on 27 June 2000. Permission was granted on 4 January 2001, 6 months later. The site became operational on 30 July 2002, 19 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2630.