Renewable sitesCrugmore Farm

Crugmore Farm

Crugmore Farm is an operational 6.4 MW solar farm in Ceredigion, generating since 25 March 2015. Planning permission was granted on 24 February 2014, 4 months after submission. Operator of record: John Laing Environmental Assets Group.

6.4 MW
Capacity
as recorded in REPD
Operational
Status
since 25 March 2015
Solar Photovoltaics
Technology
John Laing Environmental Assets Group
Ceredigion
Authority
Wales

Planning and build timeline

Application submitted25 October 2013
Permission granted24 February 2014
4 months after submission
Operational25 March 2015
13 months after consent

Screening a site of your own?

RedlineUK · £39

Ceredigion approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Crugmore Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Ceredigion’s record on solar

Ceredigion has decided 11 solar farms and approved 100%, taking a median of 6.4 months. See every solar farm decision in Ceredigion

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.55.3 km
Solar Photovoltaics · Operational
16.3 km
Solar Photovoltaics · Operational
86.9 km

How big is Crugmore Farm?

Crugmore Farm has a recorded installed capacity of 6.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Crugmore Farm?

REPD records the operator as John Laing Environmental Assets Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Crugmore Farm approved and built?

The application was submitted on 25 October 2013. Permission was granted on 24 February 2014, 4 months later. The site became operational on 25 March 2015, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5233.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode