Llwyn Du Solar Farm
Llwyn Du Solar Farm is an operational 8 MW solar farm in Ceredigion, generating since 26 February 2015. Planning permission was granted on 20 January 2014, 6 months after submission. Operator of record: Next Energy Solar Fund.
Planning and build timeline
| Application submitted | 8 July 2013 |
| Permission granted | 20 January 2014 6 months after submission |
| Operational | 26 February 2015 13 months after consent |
Screening a site of your own?
Ceredigion approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Llwyn Du Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
Ceredigion’s record on solar
Ceredigion has decided 11 solar farms and approved 100%, taking a median of 6.4 months. See every solar farm decision in Ceredigion →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1.5 | 3.2 km |
Solar Photovoltaics · Operational | 6.4 | 6.9 km |
Solar Photovoltaics · Operational | 1 | 10.5 km |
Wind Onshore · Operational | 3.9 | 13.6 km |
How big is Llwyn Du Solar Farm?
Llwyn Du Solar Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Llwyn Du Solar Farm?
REPD records the operator as Next Energy Solar Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Llwyn Du Solar Farm approved and built?
The application was submitted on 8 July 2013. Permission was granted on 20 January 2014, 6 months later. The site became operational on 26 February 2015, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1827.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode