Novarly ParcelRenewable sites

Renewable sitesReydon Farm

Reydon Farm

Reydon Farm is operational in East Suffolk with a recorded capacity of 3.9 MW, and has been generating since 2015-03-15.

3.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-15
Solar Photovoltaics
Technology
Green Hedge (BayWa r.e.)
East Suffolk
Authority
England

Planning and build timeline

Application submitted2013-03-11
Permission granted2013-06-06
3 months after submission
Operational2015-03-15
21 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Suffolk’s record on solar

East Suffolk has decided 33 solar farms and approved 97%, taking a median of 3 months. See every solar farm decision in East Suffolk

Other built sites within 15 km

SiteMWDistance
Upper Holton Wind Farm
Wind Onshore · Operational
11.58.4 km
Holton Airfield
Solar Photovoltaics · Operational
118.5 km
Wind Farm Africa Alive
Wind Onshore · Operational
4.19.1 km
Norwich Road Industrial Estate
Battery · Under Construction
509.6 km
Ellough Airfield (Resubmission)
Solar Photovoltaics · Operational
13.210.8 km
Ellough Airfield (Ellough 2 extension)
Solar Photovoltaics · Operational
1011.3 km
Promens Solar
Solar Photovoltaics · Operational
1.711.4 km
Playters Solar Farm
Solar Photovoltaics · Operational
8.611.7 km

How big is Reydon Farm?

Reydon Farm has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Reydon Farm?

REPD records the operator as Green Hedge (BayWa r.e.). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Reydon Farm approved and built?

The application was submitted on 2013-03-11. Permission was granted on 2013-06-06, 3 months later. The site became operational on 2015-03-15, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1751.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council