Renewable sites › Norwich Road Industrial Estate
Norwich Road Industrial Estate
Norwich Road Industrial Estate is under construction in East Suffolk with a recorded capacity of 50 MW.
Planning and build timeline
| Application submitted | 2021-02-03 |
| Permission granted | 2021-03-26 2 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Suffolk’s record on battery storage
East Suffolk has decided 6 battery storage schemes and approved 100%, taking a median of 4.5 months. See every battery storage scheme decision in East Suffolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Holton Airfield Solar Photovoltaics · Operational | 11 | 1.3 km |
Upper Holton Wind Farm Wind Onshore · Operational | 11.5 | 1.9 km |
Chediston Hall Solar Park Solar Photovoltaics · Operational | 12.3 | 2.4 km |
Reydon Farm Solar Photovoltaics · Operational | 3.9 | 9.6 km |
Playters Solar Farm Solar Photovoltaics · Operational | 8.6 | 10.7 km |
Promens Solar Solar Photovoltaics · Operational | 1.7 | 10.8 km |
Ellough Airfield (Resubmission) Solar Photovoltaics · Operational | 13.2 | 10.9 km |
Ellough Airfield (Ellough 2 extension) Solar Photovoltaics · Operational | 10 | 11.3 km |
How big is Norwich Road Industrial Estate?
Norwich Road Industrial Estate has a recorded installed capacity of 50 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Norwich Road Industrial Estate?
REPD records the operator as Eelpower Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Norwich Road Industrial Estate approved and built?
The application was submitted on 2021-02-03. Permission was granted on 2021-03-26, 2 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12529.