Novarly ParcelRenewable sites

Renewable sitesPentland Road Wind Farm

Pentland Road Wind Farm

Pentland Road Wind Farm is an operational 13.8 MW onshore wind farm in Na h-Eileanan Siar, generating since 28 March 2013. Planning permission was granted on 6 September 2004, 23 months after submission. Operator of record: Arnish Electric Ltd / Farm Energy Ltd.

13.8 MW
Capacity
as recorded in REPD
Operational
Status
since 28 March 2013
Wind Onshore
Technology
Arnish Electric Ltd / Farm Energy Ltd
Na h-Eileanan Siar
Authority
Scotland

Planning and build timeline

Application submitted30 September 2002
Permission granted6 September 2004
23 months after submission
Operational28 March 2013
103 months after consent

Screening a site of your own?

RedlineUK · £39

Na h-Eileanan Siar approves 83% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pentland Road Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Na h-Eileanan Siar’s record on onshore wind

Na h-Eileanan Siar has decided 12 onshore wind schemes and approved 83%, taking a median of 18.9 months. See every onshore wind scheme decision in Na h-Eileanan Siar

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
95.8 km
Wind Onshore · Operational
3.99.9 km
Wind Onshore · Operational
2.714.1 km

How big is Pentland Road Wind Farm?

Pentland Road Wind Farm has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pentland Road Wind Farm?

REPD records the operator as Arnish Electric Ltd / Farm Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pentland Road Wind Farm approved and built?

The application was submitted on 30 September 2002. Permission was granted on 6 September 2004, 23 months later. The site became operational on 28 March 2013, 103 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4063.