Renewable sites › Loch Sminig Wind Project
Loch Sminig Wind Project
Loch Sminig Wind Project is operational in Na h-Eileanan Siar with a recorded capacity of 2.7 MW, and has been generating since 2015-09-15.
Planning and build timeline
| Application submitted | 2008-08-29 |
| Permission granted | 2009-05-06 8 months after submission |
| Operational | 2015-09-15 76 months after consent |
Na h-Eileanan Siar’s record on onshore wind
Na h-Eileanan Siar has decided 12 onshore wind schemes and approved 83%, taking a median of 18.9 months. See every onshore wind scheme decision in Na h-Eileanan Siar →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pentland Road Wind Farm Wind Onshore · Operational | 13.8 | 14.1 km |
How big is Loch Sminig Wind Project?
Loch Sminig Wind Project has a recorded installed capacity of 2.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Loch Sminig Wind Project?
REPD records the operator as Urras Oighreachd Ghabhsainn. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Loch Sminig Wind Project approved and built?
The application was submitted on 2008-08-29. Permission was granted on 2009-05-06, 8 months later. The site became operational on 2015-09-15, 76 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3988.