Point Wind / Beinn Ghrideag Farm is an operational 9 MW onshore wind farm in Na h-Eileanan Siar, generating since 17 July 2015. Planning permission was granted on 26 April 2012, 44 months after submission. Operator of record: Point Power & Energy Ltd / SgurrEnergy.

9 MW
Capacity
as recorded in REPD
Operational
Status
since 17 July 2015
Wind Onshore
Technology
Point Power & Energy Ltd / SgurrEnergy
Na h-Eileanan Siar
Authority
Scotland

Planning and build timeline

Application submitted13 August 2008
Permission granted26 April 2012
44 months after submission
Operational17 July 2015
39 months after consent

Screening a site of your own?

RedlineUK · £39

Na h-Eileanan Siar approves 83% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Point Wind / Beinn Ghrideag Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Na h-Eileanan Siar’s record on onshore wind

Na h-Eileanan Siar has decided 12 onshore wind schemes and approved 83%, taking a median of 18.9 months. See every onshore wind scheme decision in Na h-Eileanan Siar

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
3.94.3 km
Wind Onshore · Operational
13.85.8 km

How big is Point Wind / Beinn Ghrideag Farm?

Point Wind / Beinn Ghrideag Farm has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Point Wind / Beinn Ghrideag Farm?

REPD records the operator as Point Power & Energy Ltd / SgurrEnergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Point Wind / Beinn Ghrideag Farm approved and built?

The application was submitted on 13 August 2008. Permission was granted on 26 April 2012, 44 months later. The site became operational on 17 July 2015, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4272.

Novarly Parcel · official public data, read properly · parcel.novarly.com