Onshore wind planning in Na h-Eileanan Siar

Na h-Eileanan Siar has decided 12 onshore wind schemes and approved 83% of them, taking a median of 18.9 months to decide. Consented capacity: 96 MW. 3 applications still awaiting a decision.

83%
Approved
10 granted · 2 refused
18.9 mo
Median decision
UK 11.5 mo
96 MW
Consented
4 MW refused
0
Appeals
no appeals recorded

How Na h-Eileanan Siar compares

Against the 75 UK authorities with 5+ onshore wind decisions, Na h-Eileanan Siar sits in the 82nd percentile for approval rate (15 points above the England average) and the 22nd percentile for speed.

Decisions by year

35Approved — 1 (2011)111Approved — 1 (2012)112Refused — 1 (2013)113Refused — 1 (2014)114Approved — 1 (2019)119Approved — 1 (2020)120Approved — 1 (2022)122Approved — 1 (2025)125
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (17)

SchemeMWStatusDecided
Monan Wind Farm, Ceann An Ora - Wind Turbines
Monan Wind Company Limited · 24/00123/PPW · 11.5 mo to decide
Awaiting Construction2025-03-26
Druim Leathann Windfarm
Baywa R.E. UK Limited · 18/00216/PPDM · 48.5 mo to decide
48.3Awaiting Construction2022-06-22
Lochdar Hill Wind Farm
Storas Uibhist · 15/00515/PPW
6.9Application Withdrawn2020-06-26
Beinn Thulabaigh Wind Turbine
Knock and Swordale Community Company · 19/00209/PPW · 12.5 mo to decide
5Awaiting Construction2020-05-21
Sandwick North St Community wind turbine
SgurrEnergy · 33.5 mo to decide
5Awaiting Construction2019-11-05
Sandwick East Community Wind Farm
Aquatera · 9/00189/PPDM
49.9Application Submitted2019-04-29
Druim Leathann
BayWa r.e. (formerly Forsa) · 17/00282/PPDM
49.7Revised2017-06-02
Locheport wind turbines
North Uist Development Company · 13/00155/PPD · 18.2 mo to decide
1.8Application Refused2014-10-09
Druim Leathann Wind Farm
Forsa (formerly 2020 Renewables/Velocita) · 13/00215/PPDM · 7.2 mo to decide
42Revised2013-12-05
Kirkibost Wind Farm
Private Developer · 11/00380/PPD · 17.7 mo to decide
1.8Application Refused2013-01-28
Point Wind / Beinn Ghrideag Farm
Point Power & Energy Ltd / SgurrEnergy · 08/00371/PPD · 44.4 mo to decide
9Operational2012-04-26
Lochcarnan Community Windfarm
Storas Uibhist · 08/00561/FUL · 36.5 mo to decide
6.9Operational2011-12-21
Loch Sminig Wind Project
Urras Oighreachd Ghabhsainn · 08/00407/PPD · 8.2 mo to decide
2.7Operational2009-05-06
North Harris Community Trust
North Harris Community Trust · 19.6 mo to decide
2.5Abandoned2008-02-18
Monan Hill Wind Turbines
North Harris Trust · 06/00290/FUL · 20.7 mo to decide
1.5Operational2008-02-14
Pentland Road Wind Farm
Arnish Electric Ltd / Farm Energy Ltd · 02/00404/PPD · 23.2 mo to decide
13.8Operational2004-09-06
Arnish Moor
Arnish Electric Ltd / Farm Energy · 3 mo to decide
3.9Operational2001-09-01

Does Na h-Eileanan Siar approve onshore wind schemes?

Yes — of the 12 onshore wind schemes Na h-Eileanan Siar has decided, 83% were approved (10 granted, 2 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Na h-Eileanan Siar?

The median time from application to decision is 18.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Na h-Eileanan Siar consented?

96 MW has been consented across 10 approved schemes, with 4 MW refused. A further 3 applications awaits a decision.

Other technologies in Na h-Eileanan Siar

Solar in Na h-Eileanan SiarBattery storage in Na h-Eileanan Siar

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.