Renewable sites › PARK WOOD SOLAR FARM
PARK WOOD SOLAR FARM
PARK WOOD SOLAR FARM is operational in Somerset with a recorded capacity of 5 MW, and has been generating since 2011-09-29.
Planning and build timeline
| Application submitted | 2011-05-04 |
| Permission granted | 2011-07-28 3 months after submission |
| Operational | 2011-09-29 2 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Nutrient-neutrality catchment — Brue Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Somerset’s record on solar
Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Higher Hill Farm (extension) Solar Photovoltaics · Operational | 1.5 | 3.3 km |
Higher Hill Farm Energy Storage Battery · Operational | 0.3 | 3.3 km |
Higher Hill Farm Solar Photovoltaics · Operational | 5 | 3.4 km |
Manor Farm (Keinton Mandeville) Solar Photovoltaics · Operational | 1 | 4.5 km |
Tout Lane, Charlton Adam - Solar Photovoltaic System Solar Photovoltaics · Operational | 0.3 | 6.1 km |
Somerton Door Farm Solar Photovoltaics · Operational | 8.7 | 7.3 km |
Whitley Farm (2 of 2) Solar Photovoltaics · Operational | 3.5 | 8.2 km |
Dimmer Anaerobic Digestor (Waste AD) Anaerobic Digestion · Operational | 3 | 8.6 km |
How big is PARK WOOD SOLAR FARM?
PARK WOOD SOLAR FARM has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates PARK WOOD SOLAR FARM?
REPD records the operator as Solar Power Generation Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was PARK WOOD SOLAR FARM approved and built?
The application was submitted on 2011-05-04. Permission was granted on 2011-07-28, 3 months later. The site became operational on 2011-09-29, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1076.
Novarly Parcel · official public data, read properly · parcel.novarly.com