Renewable sites › Dimmer Anaerobic Digestor (Waste AD)
Dimmer Anaerobic Digestor (Waste AD)
Dimmer Anaerobic Digestor (Waste AD) is operational in Somerset with a recorded capacity of 3 MW, and has been generating since 2013-10-01.
Planning and build timeline
| Application submitted | 2004-08-13 |
| Permission granted | 2004-12-10 4 months after submission |
| Operational | 2013-10-01 106 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Brue Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dimmer Landfill Gas Scheme Landfill Gas · Operational | 2.3 | 0.5 km |
Dimmer Landfill Site Landfill Gas · Operational | 1.9 | 0.6 km |
Manor Farm (Castle Cary) Solar Photovoltaics · Operational | 1.8 | 3.2 km |
Manor Farm (Keinton Mandeville) Solar Photovoltaics · Operational | 1 | 6.1 km |
Wyke Farms Biogas (Farm AD) Anaerobic Digestion · Operational | 1 | 6.3 km |
Pylle Southern solar park (Lower Easton Farm) Solar Photovoltaics · Operational | 5 | 7.5 km |
Sutton Montis Road Solar Park / Sutton Bridge Solar Farm Solar Photovoltaics · Operational | 5.4 | 7.5 km |
Tout Lane, Charlton Adam - Solar Photovoltaic System Solar Photovoltaics · Operational | 0.3 | 8.2 km |
How big is Dimmer Anaerobic Digestor (Waste AD)?
Dimmer Anaerobic Digestor (Waste AD) has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dimmer Anaerobic Digestor (Waste AD)?
REPD records the operator as Viridor / Wyvern Waste Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dimmer Anaerobic Digestor (Waste AD) approved and built?
The application was submitted on 2004-08-13. Permission was granted on 2004-12-10, 4 months later. The site became operational on 2013-10-01, 106 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 294.