Renewable sitesOsbaldwick Substation

Osbaldwick Substation

Osbaldwick Substation is an operational 49.9 MW battery storage site in York, generating since 1 January 2024. Planning permission was granted on 8 October 2020, 2 months after submission. Operator of record: UK Battery Storage.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 2024
Battery
Technology
UK Battery Storage
York
Authority
England

Planning and build timeline

Application submitted21 August 2020
Permission granted8 October 2020
2 months after submission
Operational1 January 2024
39 months after consent

Screening a site of your own?

RedlineUK · £39

York approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Osbaldwick Substation’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

York’s record on battery storage

York has decided 5 battery storage schemes and approved 100%, taking a median of 6.9 months. See every battery storage scheme decision in York

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.165.1 km
Anaerobic Digestion · Operational
18 km
Landfill Gas · Operational
2.410 km

How big is Osbaldwick Substation?

Osbaldwick Substation has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Osbaldwick Substation?

REPD records the operator as UK Battery Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Osbaldwick Substation approved and built?

The application was submitted on 21 August 2020. Permission was granted on 8 October 2020, 2 months later. The site became operational on 1 January 2024, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7172.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode