Osbaldwick Substation
Osbaldwick Substation is an operational 49.9 MW battery storage site in York, generating since 1 January 2024. Planning permission was granted on 8 October 2020, 2 months after submission. Operator of record: UK Battery Storage.
Planning and build timeline
| Application submitted | 21 August 2020 |
| Permission granted | 8 October 2020 2 months after submission |
| Operational | 1 January 2024 39 months after consent |
Screening a site of your own?
York approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Osbaldwick Substation’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — York
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
York’s record on battery storage
York has decided 5 battery storage schemes and approved 100%, taking a median of 6.9 months. See every battery storage scheme decision in York →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 0.16 | 5.1 km |
Anaerobic Digestion · Operational | 1 | 8 km |
Landfill Gas · Operational | 2.4 | 10 km |
How big is Osbaldwick Substation?
Osbaldwick Substation has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Osbaldwick Substation?
REPD records the operator as UK Battery Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Osbaldwick Substation approved and built?
The application was submitted on 21 August 2020. Permission was granted on 8 October 2020, 2 months later. The site became operational on 1 January 2024, 39 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7172.