Renewable sites › Kingsway - Solar Panels
Kingsway - Solar Panels
Kingsway - Solar Panels is operational in York with a recorded capacity of 0.16 MW, and has been generating since 2022-10-11.
Planning and build timeline
| Application submitted | 2022-05-06 |
| Permission granted | 2022-12-15 7 months after submission |
| Operational | 2022-10-11 |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
York’s record on solar
York has decided 29 solar farms and approved 97%, taking a median of 1.8 months. See every solar farm decision in York →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Osbaldwick Substation Battery · Operational | 49.9 | 5.1 km |
Harewood Whin Landfill Site Landfill Gas · Operational | 2.4 | 5.5 km |
Gravel Pit Farm Anaerobic Digestion · Operational | 1 | 10.3 km |
Mill Hill Farm Solar Photovoltaics · Operational | 5 | 14.2 km |
How big is Kingsway - Solar Panels?
Kingsway - Solar Panels has a recorded installed capacity of 0.16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kingsway - Solar Panels?
REPD records the operator as Solar Options For Schools Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kingsway - Solar Panels approved and built?
The application was submitted on 2022-05-06. Permission was granted on 2022-12-15, 7 months later. The site became operational on 2022-10-11.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11271.
Novarly Parcel · official public data, read properly · parcel.novarly.com