Harewood Whin Landfill Site is operational in York with a recorded capacity of 2.4 MW, and has been generating since 1997-12-11.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1997-12-11
Landfill Gas
Technology
Yorwaste /Biogas
York
Authority
England

Planning and build timeline

Application submitted1994-08-10
Permission granted1994-12-02
4 months after submission
Operational1997-12-11
36 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Kingsway - Solar Panels
Solar Photovoltaics · Operational
0.165.5 km
Osbaldwick Substation
Battery · Operational
49.910 km

How big is Harewood Whin Landfill Site?

Harewood Whin Landfill Site has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Harewood Whin Landfill Site?

REPD records the operator as Yorwaste /Biogas. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Harewood Whin Landfill Site approved and built?

The application was submitted on 1994-08-10. Permission was granted on 1994-12-02, 4 months later. The site became operational on 1997-12-11, 36 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 762.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council