Monksham Solar Farm is an operational 10.7 MW solar farm in Somerset, generating since 30 March 2014. Planning permission was granted on 17 September 2013, 4 months after submission. Operator of record: John Laing Environmental Assets Group.

10.7 MW
Capacity
as recorded in REPD
Operational
Status
since 30 March 2014
Solar Photovoltaics
Technology
John Laing Environmental Assets Group
Somerset
Authority
England

Planning and build timeline

Application submitted16 May 2013
Permission granted17 September 2013
4 months after submission
Operational30 March 2014
6 months after consent

Screening a site of your own?

RedlineUK · £39

Somerset approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Monksham Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
51.7 km
Solar Photovoltaics · Operational
63.7 km
Solar Photovoltaics · Operational
1.58.8 km
Solar Photovoltaics · Under Construction
1.7810.5 km
Solar Photovoltaics · Under Construction
512.1 km
Anaerobic Digestion · Operational
113.1 km
Solar Photovoltaics · Operational
3.913.6 km
Solar Photovoltaics · Operational
4.713.6 km

How big is Monksham Solar Farm?

Monksham Solar Farm has a recorded installed capacity of 10.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Monksham Solar Farm?

REPD records the operator as John Laing Environmental Assets Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Monksham Solar Farm approved and built?

The application was submitted on 16 May 2013. Permission was granted on 17 September 2013, 4 months later. The site became operational on 30 March 2014, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2039.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode