Renewable sites › West Woodlands
West Woodlands
West Woodlands is operational in Somerset with a recorded capacity of 5 MW, and has been generating since 2016-03-23.
Planning and build timeline
| Application submitted | 2014-11-20 |
| Permission granted | 2015-08-24 9 months after submission |
| Operational | 2016-03-23 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Somerset’s record on solar
Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Monksham Solar Farm Solar Photovoltaics · Operational | 10.7 | 1.7 km |
Holwell Hill Solar Photovoltaics · Operational | 6 | 4.6 km |
Land at Soho Farm Solar Photovoltaics · Operational | 1.5 | 9.2 km |
Burges Lane, Stoke St Michael - Solar Array Panels Solar Photovoltaics · Under Construction | 1.78 | 11.4 km |
Brook Hall Farm Solar Photovoltaics · Operational | 4.7 | 12 km |
Land at Poles Hole Farm Solar Photovoltaics · Operational | 6.8 | 12.2 km |
Blenches Mill Solar Photovoltaics · Operational | 6.1 | 12.6 km |
Lodge Farm Solar Farm Solar Photovoltaics · Under Construction | 5 | 13.1 km |
How big is West Woodlands?
West Woodlands has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates West Woodlands?
REPD records the operator as Sunsave 24/ Vogt solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was West Woodlands approved and built?
The application was submitted on 2014-11-20. Permission was granted on 2015-08-24, 9 months later. The site became operational on 2016-03-23, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4889.