Millour Hill Community Windfarm

Millour Hill Community Windfarm is an operational 18 MW onshore wind farm in North Ayrshire, generating since 1 May 2012. Planning permission was granted on 16 December 2009, 6 months after submission. Operator of record: Community Windpower.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 2012
Wind Onshore
Technology
Community Windpower
North Ayrshire
Authority
Scotland

Planning and build timeline

Application submitted25 June 2009
Permission granted16 December 2009
6 months after submission
Operational1 May 2012
28 months after consent

Screening a site of your own?

RedlineUK · £39

North Ayrshire approves 78% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Millour Hill Community Windfarm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

North Ayrshire’s record on onshore wind

North Ayrshire has decided 18 onshore wind schemes and approved 78%, taking a median of 8.5 months. See every onshore wind scheme decision in North Ayrshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
6.40.7 km
Wind Onshore · Operational
181.3 km
Wind Onshore · Operational
283.5 km
Anaerobic Digestion · Operational
2.23.8 km
Landfill Gas · Operational
1.23.8 km
Wind Onshore · Under Construction
97.5 km
Solar Photovoltaics · Operational
58.4 km
Wind Onshore · Operational
69.9 km

How big is Millour Hill Community Windfarm?

Millour Hill Community Windfarm has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Millour Hill Community Windfarm?

REPD records the operator as Community Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Millour Hill Community Windfarm approved and built?

The application was submitted on 25 June 2009. Permission was granted on 16 December 2009, 6 months later. The site became operational on 1 May 2012, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3690.