Renewable sites › Barkip Anaerobic Digestor (Waste AD)
Barkip Anaerobic Digestor (Waste AD)
Barkip Anaerobic Digestor (Waste AD) is operational in North Ayrshire with a recorded capacity of 2.2 MW, and has been generating since 2012-05-11.
Planning and build timeline
| Application submitted | 2009-09-02 |
| Permission granted | 2009-10-15 1 months after submission |
| Operational | 2012-05-11 31 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Barkip Landfill Site Landfill Gas · Operational | 1.2 | 0 km |
Millour Hill Community Windfarm Wind Onshore · Operational | 18 | 3.8 km |
Millour Hill Community Windfarm (Extension) Wind Onshore · Operational | 6.4 | 4.4 km |
Wardlaw Wood Wind Onshore · Operational | 18 | 4.5 km |
Site To North East Of, Lochcraigs Farm Solar Photovoltaics · Operational | 5 | 6.9 km |
Kelburn Wind Onshore · Operational | 28 | 7 km |
Sorbie Farm Wind Onshore · Under Construction | 9 | 7.5 km |
Ardrossan Extension Wind Onshore · Operational | 6 | 9.9 km |
How big is Barkip Anaerobic Digestor (Waste AD)?
Barkip Anaerobic Digestor (Waste AD) has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Barkip Anaerobic Digestor (Waste AD)?
REPD records the operator as Scottish and Southern Energy (SSE) / William Tracey Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Barkip Anaerobic Digestor (Waste AD) approved and built?
The application was submitted on 2009-09-02. Permission was granted on 2009-10-15, 1 months later. The site became operational on 2012-05-11, 31 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 266.