Renewable sites › Ardrossan Extension
Ardrossan Extension
Ardrossan Extension is operational in North Ayrshire with a recorded capacity of 6 MW, and has been generating since 2008-11-01.
Planning and build timeline
| Application submitted | 2005-12-01 |
| Permission granted | 2007-11-26 24 months after submission |
| Operational | 2008-11-01 11 months after consent |
North Ayrshire’s record on onshore wind
North Ayrshire has decided 18 onshore wind schemes and approved 78%, taking a median of 8.5 months. See every onshore wind scheme decision in North Ayrshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ardrossan Wind Onshore · Operational | 24 | 0 km |
Sorbie Farm Wind Onshore · Under Construction | 9 | 2.4 km |
Site To North East Of, Lochcraigs Farm Solar Photovoltaics · Operational | 5 | 4.2 km |
Wardlaw Wood Wind Onshore · Operational | 18 | 8.8 km |
Nethermains - Solar Farm Solar Photovoltaics · Under Construction | 7.5 | 9 km |
Millour Hill Community Windfarm Wind Onshore · Operational | 18 | 9.9 km |
Barkip Landfill Site Landfill Gas · Operational | 1.2 | 9.9 km |
Barkip Anaerobic Digestor (Waste AD) Anaerobic Digestion · Operational | 2.2 | 9.9 km |
How big is Ardrossan Extension?
Ardrossan Extension has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ardrossan Extension?
REPD records the operator as Airtricity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ardrossan Extension approved and built?
The application was submitted on 2005-12-01. Permission was granted on 2007-11-26, 24 months later. The site became operational on 2008-11-01, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4668.