Kelburn
Kelburn is an operational 28 MW onshore wind farm in North Ayrshire, generating since 2 May 2012. Planning permission was granted on 10 August 2009, 61 months after submission. Operator of record: Renewable Energy Systems (RES).
Planning and build timeline
| Application submitted | 9 July 2004 |
| Permission granted | 10 August 2009 61 months after submission |
| Operational | 2 May 2012 33 months after consent |
Screening a site of your own?
North Ayrshire approves 78% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Kelburn’s recorded coordinate — swap in your own postcode or coordinates.
North Ayrshire’s record on onshore wind
North Ayrshire has decided 18 onshore wind schemes and approved 78%, taking a median of 8.5 months. See every onshore wind scheme decision in North Ayrshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 6.4 | 2.8 km |
Wind Onshore · Operational | 18 | 3.5 km |
Wind Onshore · Operational | 18 | 3.9 km |
Anaerobic Digestion · Operational | 2.2 | 7 km |
Landfill Gas · Operational | 1.2 | 7 km |
Wind Onshore · Under Construction | 9 | 10.4 km |
Solar Photovoltaics · Operational | 5 | 11.7 km |
Wind Onshore · Operational | 6 | 12.5 km |
How big is Kelburn?
Kelburn has a recorded installed capacity of 28 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kelburn?
REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kelburn approved and built?
The application was submitted on 9 July 2004. Permission was granted on 10 August 2009, 61 months later. The site became operational on 2 May 2012, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3149.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode