Renewable sites › Kelburn
Kelburn
Kelburn is operational in North Ayrshire with a recorded capacity of 28 MW, and has been generating since 2012-05-02.
Planning and build timeline
| Application submitted | 2004-07-09 |
| Permission granted | 2009-08-10 61 months after submission |
| Operational | 2012-05-02 33 months after consent |
North Ayrshire’s record on onshore wind
North Ayrshire has decided 18 onshore wind schemes and approved 78%, taking a median of 8.5 months. See every onshore wind scheme decision in North Ayrshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Millour Hill Community Windfarm (Extension) Wind Onshore · Operational | 6.4 | 2.8 km |
Millour Hill Community Windfarm Wind Onshore · Operational | 18 | 3.5 km |
Wardlaw Wood Wind Onshore · Operational | 18 | 3.9 km |
Barkip Anaerobic Digestor (Waste AD) Anaerobic Digestion · Operational | 2.2 | 7 km |
Barkip Landfill Site Landfill Gas · Operational | 1.2 | 7 km |
Sorbie Farm Wind Onshore · Under Construction | 9 | 10.4 km |
Site To North East Of, Lochcraigs Farm Solar Photovoltaics · Operational | 5 | 11.7 km |
Ardrossan Extension Wind Onshore · Operational | 6 | 12.5 km |
How big is Kelburn?
Kelburn has a recorded installed capacity of 28 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kelburn?
REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kelburn approved and built?
The application was submitted on 2004-07-09. Permission was granted on 2009-08-10, 61 months later. The site became operational on 2012-05-02, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3149.