Hook Valley Solar Park

Hook Valley Solar Park is an operational 17 MW solar farm in Somerset, generating since 31 March 2014. Planning permission was granted on 26 September 2013, 10 months after submission. Operator of record: British Solar Renewables (formerly know as Solar Power Generation).

17 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2014
Solar Photovoltaics
Technology
British Solar Renewables (formerly know as Solar Power Generation)
Somerset
Authority
England

Planning and build timeline

Application submitted21 November 2012
Permission granted26 September 2013
10 months after submission
Operational31 March 2014
6 months after consent

Screening a site of your own?

RedlineUK · £39

Somerset approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hook Valley Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
3.50.8 km
Solar Photovoltaics · Operational
1.51.8 km
Solar Photovoltaics · Operational
53.4 km
Solar Photovoltaics · Operational
56.2 km
Solar Photovoltaics · Operational
1.86.4 km
Solar Photovoltaics · Operational
57.4 km
Anaerobic Digestion · Operational
17.7 km
Solar Photovoltaics · Operational
58.2 km

How big is Hook Valley Solar Park?

Hook Valley Solar Park has a recorded installed capacity of 17 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hook Valley Solar Park?

REPD records the operator as British Solar Renewables (formerly know as Solar Power Generation). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hook Valley Solar Park approved and built?

The application was submitted on 21 November 2012. Permission was granted on 26 September 2013, 10 months later. The site became operational on 31 March 2014, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2005.