Novarly ParcelRenewable sites

Renewable sitesMerevale & Blyth Estate (Biomass Plant)

Merevale & Blyth Estate (Biomass Plant)

Merevale & Blyth Estate (Biomass Plant) is operational in North Warwickshire with a recorded capacity of 2.5 MW, and has been generating since 2015-03-28.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-28
Biomass (dedicated)
Technology
Merevale and Blyth Estates
North Warwickshire
Authority
England

Planning and build timeline

Application submitted2010-12-06
Permission granted2011-03-28
4 months after submission
Operational2015-03-28
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Merevale & Blyth Estate (Waste AD)
Anaerobic Digestion · Operational
20.1 km
Atherstone
Solar Photovoltaics · Operational
14.75 km
Ld NW Of Ratcliffe House Farm
Solar Photovoltaics · Operational
3.55.9 km
Wilnecote Landfill Site
Landfill Gas · Operational
17.4 km
Land South of Pogmore Spinney
Solar Photovoltaics · Operational
58.2 km
Austrey House Farm
Anaerobic Digestion · Operational
1.58.3 km
Judkins Landfill Scheme
Landfill Gas · Operational
2.78.3 km
Judkins Landfill Site Phase 3
Landfill Gas · Operational
1.28.4 km

How big is Merevale & Blyth Estate (Biomass Plant)?

Merevale & Blyth Estate (Biomass Plant) has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Merevale & Blyth Estate (Biomass Plant)?

REPD records the operator as Merevale and Blyth Estates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Merevale & Blyth Estate (Biomass Plant) approved and built?

The application was submitted on 2010-12-06. Permission was granted on 2011-03-28, 4 months later. The site became operational on 2015-03-28, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 114.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council