Renewable sites › Meall an Tuirc Wind Farm
Meall an Tuirc Wind Farm
Meall an Tuirc Wind Farm is an operational 17 MW onshore wind farm in Highland, generating since 1 September 1997. Planning permission was granted on 27 August 1996, 15 months after submission. Operator of record: RWE npower.
Planning and build timeline
| Application submitted | 17 May 1995 |
| Permission granted | 27 August 1996 15 months after submission |
| Operational | 1 September 1997 12 months after consent |
Screening a site of your own?
Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Meall an Tuirc Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 36.8 | 0 km |
Wind Onshore · Operational | 9 | 0.5 km |
Small Hydro · Operational | 3.5 | 6.4 km |
Wind Onshore · Operational | 29.9 | 7.4 km |
Solar Photovoltaics · Under Construction | 0.5 | 10.6 km |
Wind Onshore · Operational | 29.8 | 12.1 km |
Wind Onshore · Operational | 4.6 | 13.8 km |
How big is Meall an Tuirc Wind Farm?
Meall an Tuirc Wind Farm has a recorded installed capacity of 17 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Meall an Tuirc Wind Farm?
REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Meall an Tuirc Wind Farm approved and built?
The application was submitted on 17 May 1995. Permission was granted on 27 August 1996, 15 months later. The site became operational on 1 September 1997, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3297.
Novarly Parcel · official public data, read properly · parcel.novarly.com