Black Rock

Black Rock is an operational 3.5 MW hydro scheme in Highland, generating since 1 June 2012. Planning permission was granted on 4 December 2008, 23 months after submission. Operator of record: RWE npower.

3.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 June 2012
Small Hydro
Technology
RWE npower
Highland
Authority
Scotland

Planning and build timeline

Application submitted20 December 2006
Permission granted4 December 2008
23 months after submission
Operational1 June 2012
42 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Black Rock’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
96.1 km
Wind Onshore · Operational
36.86.4 km
Wind Onshore · Operational
176.4 km
Solar Photovoltaics · Under Construction
0.56.5 km
Solar Photovoltaics · Operational
0.211.2 km
Wind Onshore · Operational
29.911.3 km
Biomass (dedicated) · Operational
512.1 km
Wind Onshore · Operational
4.614.6 km

How big is Black Rock?

Black Rock has a recorded installed capacity of 3.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Black Rock?

REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Black Rock approved and built?

The application was submitted on 20 December 2006. Permission was granted on 4 December 2008, 23 months later. The site became operational on 1 June 2012, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 485.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode