Beinn Tharsuinn Windfarm Project

Beinn Tharsuinn Windfarm Project is an operational 29.8 MW onshore wind farm in Highland, generating since 1 December 2005. Planning permission was granted on 11 February 2005, 34 months after submission. Operator of record: CRE Energy/ Scottish Power.

29.8 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2005
Wind Onshore
Technology
CRE Energy/ Scottish Power
Highland
Authority
Scotland

Planning and build timeline

Application submitted19 April 2002
Permission granted11 February 2005
34 months after submission
Operational1 December 2005
10 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Beinn Tharsuinn Windfarm Project’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
29.94.8 km
Wind Onshore · Operational
4.65.2 km
Wind Onshore · Operational
1712.1 km
Wind Onshore · Operational
36.812.1 km
Wind Onshore · Operational
912.5 km
Solar Photovoltaics · Under Construction
0.513.3 km

How big is Beinn Tharsuinn Windfarm Project?

Beinn Tharsuinn Windfarm Project has a recorded installed capacity of 29.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Beinn Tharsuinn Windfarm Project?

REPD records the operator as CRE Energy/ Scottish Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Beinn Tharsuinn Windfarm Project approved and built?

The application was submitted on 19 April 2002. Permission was granted on 11 February 2005, 34 months later. The site became operational on 1 December 2005, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4669.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode