Renewable sitesManston Solar Farm extension (Westwood)

Manston Solar Farm extension (Westwood)

Manston Solar Farm extension (Westwood) is an operational 9.2 MW solar farm in Thanet, generating since 28 March 2014. Planning permission was granted on 24 July 2013, 2 months after submission. Operator of record: Sunsave 16 Ltd/ Vogt Solar.

9.2 MW
Capacity
as recorded in REPD
Operational
Status
since 28 March 2014
Solar Photovoltaics
Technology
Sunsave 16 Ltd/ Vogt Solar
Thanet
Authority
England

Planning and build timeline

Application submitted10 May 2013
Permission granted24 July 2013
2 months after submission
Operational28 March 2014
8 months after consent

Screening a site of your own?

RedlineUK · £39

Thanet approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Manston Solar Farm extension (Westwood)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Thanet’s record on solar

Thanet has decided 20 solar farms and approved 95%, taking a median of 2.3 months. See every solar farm decision in Thanet

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
9.90.5 km
Solar Photovoltaics · Operational
0.22 km
Solar Photovoltaics · Operational
6.22.4 km
Solar Photovoltaics · Operational
0.43.1 km
Solar Photovoltaics · Operational
4.94.5 km
Solar Photovoltaics · Under Construction
334.6 km
Battery · Under Construction
2494.8 km
Battery · Operational
50.15 km

How big is Manston Solar Farm extension (Westwood)?

Manston Solar Farm extension (Westwood) has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Manston Solar Farm extension (Westwood)?

REPD records the operator as Sunsave 16 Ltd/ Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Manston Solar Farm extension (Westwood) approved and built?

The application was submitted on 10 May 2013. Permission was granted on 24 July 2013, 2 months later. The site became operational on 28 March 2014, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1359.