Renewable sites › Manor Farm (Castle Cary)
Manor Farm (Castle Cary)
Manor Farm (Castle Cary) is operational in Somerset with a recorded capacity of 1.8 MW, and has been generating since 2017-03-06.
Planning and build timeline
| Application submitted | 2014-08-11 |
| Permission granted | 2015-01-07 5 months after submission |
| Operational | 2017-03-06 26 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Parrett Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Somerset’s record on solar
Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dimmer Landfill Gas Scheme Landfill Gas · Operational | 2.3 | 3.1 km |
Dimmer Landfill Site Landfill Gas · Operational | 1.9 | 3.1 km |
Dimmer Anaerobic Digestor (Waste AD) Anaerobic Digestion · Operational | 3 | 3.2 km |
Wyke Farms Biogas (Farm AD) Anaerobic Digestion · Operational | 1 | 4 km |
Hook Valley Solar Park Solar Photovoltaics · Operational | 17 | 6.4 km |
Higher Hatherleigh Solar Farm Solar Photovoltaics · Operational | 3.5 | 7.1 km |
Pylle Southern solar park (Lower Easton Farm) Solar Photovoltaics · Operational | 5 | 7.6 km |
Higher Hatherleigh Solar Farm extension Solar Photovoltaics · Operational | 1.5 | 8.1 km |
How big is Manor Farm (Castle Cary)?
Manor Farm (Castle Cary) has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Manor Farm (Castle Cary)?
REPD records the operator as Brilliant Harvest Installations. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Manor Farm (Castle Cary) approved and built?
The application was submitted on 2014-08-11. Permission was granted on 2015-01-07, 5 months later. The site became operational on 2017-03-06, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2242.