Renewable sites › Wilkin And Sons, Factory Hill - Solar Farm
Wilkin And Sons, Factory Hill - Solar Farm
Wilkin And Sons, Factory Hill - Solar Farm is an operational 6.15 MW solar farm in Colchester, generating since 1 January 2023. Planning permission was granted on 6 June 2023, 5 months after submission. Operator of record: Wilkin & Sons Limited.
Planning and build timeline
| Application submitted | 30 December 2022 |
| Permission granted | 6 June 2023 5 months after submission |
| Operational | 1 January 2023 |
Screening a site of your own?
Colchester approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Wilkin And Sons, Factory Hill - Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Colchester’s record on solar
Colchester has decided 19 solar farms and approved 95%, taking a median of 3 months. See every solar farm decision in Colchester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 2.8 | 3.1 km |
Solar Photovoltaics · Operational | 12.2 | 3.1 km |
Solar Photovoltaics · Operational | 5.6 | 4.1 km |
Solar Photovoltaics · Operational | 5 | 5.4 km |
Solar Photovoltaics · Operational | 2.3 | 5.5 km |
Battery · Operational | — | 6.6 km |
Solar Photovoltaics · Operational | 40 | 6.6 km |
Solar Photovoltaics · Operational | 49 | 7.8 km |
How big is Wilkin And Sons, Factory Hill - Solar Farm?
Wilkin And Sons, Factory Hill - Solar Farm has a recorded installed capacity of 6.15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wilkin And Sons, Factory Hill - Solar Farm?
REPD records the operator as Wilkin & Sons Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wilkin And Sons, Factory Hill - Solar Farm approved and built?
The application was submitted on 30 December 2022. Permission was granted on 6 June 2023, 5 months later. The site became operational on 1 January 2023.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 13025.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode