London Road, Holmes Chapel Photovoltaic Panels

London Road, Holmes Chapel Photovoltaic Panels is a 0.96 MW solar farm under construction in Cheshire East. Planning permission was granted on 6 July 2021, 5 months after submission. Operator of record: Recipharm HC Limited.

0.96 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Recipharm HC Limited
Cheshire East
Authority
England

Planning and build timeline

Application submitted12 February 2021
Permission granted6 July 2021
5 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Cheshire East approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with London Road, Holmes Chapel Photovoltaic Panels’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cheshire East’s record on solar

Cheshire East has decided 36 solar farms and approved 94%, taking a median of 1.8 months. See every solar farm decision in Cheshire East

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
54.6 km
Solar Photovoltaics · Under Construction
2.58.4 km
Landfill Gas · Operational
1.610.3 km
Landfill Gas · Operational
210.3 km
Anaerobic Digestion · Operational
511.5 km
EfW Incineration · Under Construction
6012.7 km
Solar Photovoltaics · Operational
2.912.8 km
Solar Photovoltaics · Operational
5.112.9 km

How big is London Road, Holmes Chapel Photovoltaic Panels?

London Road, Holmes Chapel Photovoltaic Panels has a recorded installed capacity of 0.96 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates London Road, Holmes Chapel Photovoltaic Panels?

REPD records the operator as Recipharm HC Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was London Road, Holmes Chapel Photovoltaic Panels approved and built?

The application was submitted on 12 February 2021. Permission was granted on 6 July 2021, 5 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8452.

Novarly Parcel · official public data, read properly · parcel.novarly.com