Bentley Motors
Bentley Motors is operational in Cheshire East with a recorded capacity of 2.9 MW, and has been generating since 2018-08-01.
Planning and build timeline
| Application submitted | 2016-08-31 |
| Permission granted | 2016-11-24 3 months after submission |
| Operational | 2018-08-01 20 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cheshire East’s record on solar
Cheshire East has decided 36 solar farms and approved 94%, taking a median of 1.8 months. See every solar farm decision in Cheshire East →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bentley Motors Ltd 1 Solar Photovoltaics · Operational | 5.1 | 0.1 km |
Land To The North Of Dairy House Farm Solar Photovoltaics · Operational | 3.4 | 2.7 km |
Maw Green Landfill Site, Cheshire (Extension) Landfill Gas · Operational | 2 | 3.4 km |
Maw Green Landfill Site Landfill Gas · Operational | 1.6 | 3.4 km |
Land south of Wood Lane (Safeguard Bradwell) Solar Photovoltaics · Operational | 5 | 8.4 km |
London Road, Holmes Chapel Photovoltaic Panels Solar Photovoltaics · Under Construction | 0.96 | 12.8 km |
Combermere Abbey Solar Photovoltaics · Operational | 14 | 14.5 km |
How big is Bentley Motors?
Bentley Motors has a recorded installed capacity of 2.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bentley Motors?
REPD records the operator as Bentley Motors. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bentley Motors approved and built?
The application was submitted on 2016-08-31. Permission was granted on 2016-11-24, 3 months later. The site became operational on 2018-08-01, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6246.