Novarly ParcelRenewable sites

Renewable sitesBentley Motors

Bentley Motors

Bentley Motors is an operational 2.9 MW solar farm in Cheshire East, generating since 1 August 2018. Planning permission was granted on 24 November 2016, 3 months after submission. Operator of record: Bentley Motors.

2.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2018
Solar Photovoltaics
Technology
Bentley Motors
Cheshire East
Authority
England

Planning and build timeline

Application submitted31 August 2016
Permission granted24 November 2016
3 months after submission
Operational1 August 2018
20 months after consent

Screening a site of your own?

RedlineUK · £39

Cheshire East approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bentley Motors’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cheshire East’s record on solar

Cheshire East has decided 36 solar farms and approved 94%, taking a median of 1.8 months. See every solar farm decision in Cheshire East

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
5.10.1 km
Solar Photovoltaics · Operational
3.42.7 km
Landfill Gas · Operational
1.63.4 km
Landfill Gas · Operational
23.4 km
Solar Photovoltaics · Operational
58.4 km
Solar Photovoltaics · Under Construction
0.9612.8 km
Solar Photovoltaics · Operational
1414.5 km

How big is Bentley Motors?

Bentley Motors has a recorded installed capacity of 2.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bentley Motors?

REPD records the operator as Bentley Motors. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bentley Motors approved and built?

The application was submitted on 31 August 2016. Permission was granted on 24 November 2016, 3 months later. The site became operational on 1 August 2018, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6246.

Novarly Parcel · official public data, read properly · parcel.novarly.com