Cheshire East has decided 36 solar farms and approved 94% of them, taking a median of 1.8 months to decide. Consented capacity: 96 MW. 2 applications still awaiting a decision.
How Cheshire East compares
Against the 298 UK authorities with 5+ solar decisions, Cheshire East sits in the 38th percentile for approval rate (1 points above the England average) and the 74th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (39)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Pets At Home, Epsom Avenue - Solar PV Panels Pets at Home · 26/0672/PRIOR-14J | 0.22 | Application Submitted | 2026-02-20 |
Crewe Hall Hotel, Weston Road - Solar Panels Crewe Hall Limited · 25/3637/FUL | — | Application Submitted | 2025-10-21 |
Arclid Sand Quarry - Solar Array Bathgate Silica Sand Limited · 25/3113/PRIOR-14J · 1.8 mo to decide | 0.4 | Awaiting Construction | 2025-10-15 |
The Food Warehouse, Grand Junction Way - Solar Panels Ashcroft Electrical Service · 25/2715/PRIOR-14J · 2.5 mo to decide | 0.17 | Awaiting Construction | 2025-09-30 |
Hatherton Lodge Farm, Hunsterson Road - Solar Farm Noventum Power Limited · 24/5074/FUL · 6.1 mo to decide | 12.5 | Awaiting Construction | 2025-06-19 |
Bentley Motors, Sunnybank Road - Solar Photovoltaics Panels 3ti Energy Hubs Limited · 25/1188/PRIOR-14J · 1.8 mo to decide | 0.54 | Awaiting Construction | 2025-06-09 |
Bentley Motors, Pyms Lane - Solar Panels 3ti Energy Hubs Limited · 25/1189/PRIOR-14J · 1.1 mo to decide | 0.56 | Awaiting Construction | 2025-05-16 |
Bentley Motors Limited, Pyms Lane - Solar Panels 3ti Energy Hubs Limited · 25/1190/PRIOR-14J · 1.1 mo to decide | 1.12 | Awaiting Construction | 2025-05-16 |
Ergo Park, Pochin Way - Solar Panels Indurent PropCo C2 Limited · 24/4643/PRIOR-14J · 1.7 mo to decide | 0.19 | Awaiting Construction | 2025-05-09 |
Fields Farm, Occleston Green - Solar Panels Lachstone Farms Limited · 25/00383/P14 · 1.4 mo to decide | 0.2 | Awaiting Construction | 2025-03-25 |
Reynolds Farm, Reynolds Lane - Solar Panels JA & MH Wright · 25/0247/CLPUD · 1 mo to decide | 0.2 | Awaiting Construction | 2025-03-13 |
Church House Farm, Warmingham Road - Solar Panels Richardson Farms Limited · 24/3124N · 2.7 mo to decide | 0.15 | Awaiting Construction | 2024-11-20 |
Eagle Bridge Health and Wellbeing Centre, Dunwoody Way - Solar panels Assura Aspire Limited · 23/4708N · 1.7 mo to decide | 0.44 | Awaiting Construction | 2024-03-25 |
Bentley Motors Limited, Sunnybank Road - Solar Panels 3Ti Energy Hubs Limited · 23/3961N · 1.3 mo to decide | 0.7 | Awaiting Construction | 2023-11-27 |
Alderley Park, Congleton Road - Solar Panels Alderley Park Limited · 23/2909M · 3.4 mo to decide | 0.4 | Awaiting Construction | 2023-11-08 |
New Alderley House, Hope Drive - Solar PV System Primary Health Properties Limited · 23/3392M · 1.6 mo to decide | 0.15 | Application Refused | 2023-10-26 |
Fence House, Fence Avenue - Solar Pv Panels Armadillo Self Storage · 23/3417M · 1.3 mo to decide | 0.29 | Awaiting Construction | 2023-10-19 |
The Kings School, Alderley Road - Solar Panels The King's School · 22/3801M · 1.7 mo to decide | 0.22 | Awaiting Construction | 2022-11-18 |
The Kings School, Alderley Road - Solar Panels The King's School · 22/3802M · 1.7 mo to decide | 0.5 | Awaiting Construction | 2022-11-18 |
Barclays Bank Plc, Radbroke Solar Carport - Solar Panels Barclays Plc · 22/0560M · 7.6 mo to decide | 2.5 | Under Construction | 2022-10-04 |
Bridgemere Garden Centre,London Road - Solar Panels Blue Diamond Limited · 22/3481N · 1 mo to decide | 0.67 | Awaiting Construction | 2022-09-30 |
Building L1, Bentley Motors Limited, Pyms Lane - Solar Panels 3Ti Energy Hubs Limited · 22/1496N · 1.7 mo to decide | 0.49 | Awaiting Construction | 2022-06-01 |
Sunnybank Road - Solar Photovoltaics Panel 3Ti Energy Hubs Limited · 22/1495N · 1.6 mo to decide | 0.37 | Awaiting Construction | 2022-05-31 |
Building B2, Bentley Motors Limited, Pyms Lane - Solar PV Panels 3Ti Energy Hubs Limited · 22/1633N · 1.4 mo to decide | 0.22 | Awaiting Construction | 2022-05-26 |
Building A6, Bentley Motors Limited, Pyms Lane - Roof mounted solar photovoltaics 3Ti Energy Hubs Limited · 22/1498N · 1.4 mo to decide | 0.17 | Awaiting Construction | 2022-05-25 |
Pyms Lane - Solar PV Panels 3Ti Energy Hubs Limited · 22/1493N · 1.4 mo to decide | 0.46 | Awaiting Construction | 2022-05-25 |
Middlewich Road - Solar Photovoltaics & Battery Storage Cheshire East Council · 21/4490N · 6.7 mo to decide | 5 | Awaiting Construction | 2022-03-11 |
London Road, Holmes Chapel Photovoltaic Panels Recipharm HC Limited · 21/0777C · 4.7 mo to decide | 0.96 | Under Construction | 2021-07-06 |
Drury Lane Moss Lane Farm Solar Limited · 20/2576N · 7.3 mo to decide | 17 | Awaiting Construction | 2021-02-01 |
Bentley Motors Bentley Motors · 16/4268N · 2.8 mo to decide | 2.9 | Operational | 2016-11-24 |
Land at Moss Farm (South) TGC Renewables/NESF · 15/2126N · 12.8 mo to decide | 5 | Planning Permission Expired | 2016-05-31 |
Land at Moss Farm (North) TGC Renewables/NESF · 15/2113N · 12.4 mo to decide | 6 | Planning Permission Expired | 2016-05-20 |
Hatherton Lodge Green Switch Solutions - Liquidated · 14/4296N · 17 mo to decide | 8.3 | Planning Permission Expired | 2016-02-12 |
Land To The North Of Dairy House Farm Lightsource Renewable Energy · 15/2779N · 3.4 mo to decide | 3.4 | Operational | 2015-09-30 |
Land south of Wood Lane (Safeguard Bradwell) Lightsource Renewable Energy · 15/1541C · 5.2 mo to decide | 5 | Operational | 2015-09-04 |
Royals Wood Farm INRG Solar · 15/3380N | 5 | Abandoned | 2015-08-11 |
Hurst Hall Green Switch Solutions · 14/4380N · 2.6 mo to decide | 13.3 | Appeal Refused | 2014-12-11 |
Combermere Abbey INRG Solar · 14/2247N · 6.3 mo to decide | 14 | Operational | 2014-12-01 |
Bentley Motors Ltd 1 Bentley Motor Cars Ltd · 11/1042N · 2.8 mo to decide | 5.1 | Operational | 2011-06-08 |
Does Cheshire East approve solar farms?
Yes — of the 36 solar farms Cheshire East has decided, 94% were approved (34 granted, 2 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in Cheshire East?
The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Cheshire East consented?
96 MW has been consented across 34 approved schemes, with 13 MW refused. A further 2 applications awaits a decision.
Other technologies in Cheshire East
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com
Screen a specific site here · All authorities · UK property report