Loch Fergus Farm - Energy Storage System
Loch Fergus Farm - Energy Storage System is a 45 MW battery storage site under construction in Scotland. Planning permission was granted on 22 October 2024, 16 months after submission. Operator of record: Locogen.
Planning and build timeline
| Application submitted | 3 July 2023 |
| Permission granted | 22 October 2024 16 months after submission |
| Operational | not recorded |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Loch Fergus Farm - Energy Storage System’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on battery storage
Scottish Government (S36) has decided 108 battery storage schemes and approved 94%, taking a median of 17.3 months. See every battery storage scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 40 | 0 km |
Battery · Under Construction | 49.9 | 3.7 km |
Battery · Under Construction | 50 | 9 km |
Wind Onshore · Operational | 69 | 14.8 km |
Wind Onshore · Under Construction | 205.8 | 14.8 km |
How big is Loch Fergus Farm - Energy Storage System?
Loch Fergus Farm - Energy Storage System has a recorded installed capacity of 45 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Loch Fergus Farm - Energy Storage System?
REPD records the operator as Locogen. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Loch Fergus Farm - Energy Storage System approved and built?
The application was submitted on 3 July 2023. Permission was granted on 22 October 2024, 16 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12274.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode