Novarly ParcelRenewable sites

Renewable sitesHolmston Road - Battery Storage Facility

Holmston Road - Battery Storage Facility

Holmston Road - Battery Storage Facility is a 49.9 MW battery storage site under construction in South Ayrshire. Planning permission was granted on 30 June 2023, 3 months after submission. Operator of record: Field Energy.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Field Energy
South Ayrshire
Authority
Scotland

Planning and build timeline

Application submitted17 March 2023
Permission granted30 June 2023
3 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Ayrshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Holmston Road - Battery Storage Facility’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
403.7 km
Battery · Under Construction
453.7 km
Battery · Under Construction
5011.5 km
Biomass (dedicated) · Operational
2.611.8 km
Biomass (dedicated) · Operational
2614.2 km

How big is Holmston Road - Battery Storage Facility?

Holmston Road - Battery Storage Facility has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Holmston Road - Battery Storage Facility?

REPD records the operator as Field Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Holmston Road - Battery Storage Facility approved and built?

The application was submitted on 17 March 2023. Permission was granted on 30 June 2023, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11679.