Novarly ParcelRenewable sites

Renewable sitesLiverton Farm

Liverton Farm

Liverton Farm is an operational 4.8 MW solar farm in East Devon, generating since 19 March 2015. Planning permission was granted on 10 January 2014, 3 months after submission. Operator of record: Clinton Devon Estates.

4.8 MW
Capacity
as recorded in REPD
Operational
Status
since 19 March 2015
Solar Photovoltaics
Technology
Clinton Devon Estates
East Devon
Authority
England

Planning and build timeline

Application submitted15 October 2013
Permission granted10 January 2014
3 months after submission
Operational19 March 2015
14 months after consent

Screening a site of your own?

RedlineUK · £39

East Devon approves 87% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Liverton Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Devon’s record on solar

East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.11.7 km
Solar Photovoltaics · Operational
83.1 km
Anaerobic Digestion · Operational
16.6 km
Anaerobic Digestion · Operational
29.6 km
Solar Photovoltaics · Under Construction
3011 km
Solar Photovoltaics · Operational
1011.1 km
Solar Photovoltaics · Operational
6.512.4 km
Solar Photovoltaics · Operational
4.812.5 km

How big is Liverton Farm?

Liverton Farm has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Liverton Farm?

REPD records the operator as Clinton Devon Estates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Liverton Farm approved and built?

The application was submitted on 15 October 2013. Permission was granted on 10 January 2014, 3 months later. The site became operational on 19 March 2015, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1380.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode