Renewable sites › Littlewood Lane Solar
Littlewood Lane Solar
Littlewood Lane Solar is an operational 5 MW solar farm in Mansfield, generating since 30 March 2017. Planning permission was granted on 18 November 2015, 3 months after submission. Operator of record: Littlewood Renewables.
Planning and build timeline
| Application submitted | 18 August 2015 |
| Permission granted | 18 November 2015 3 months after submission |
| Operational | 30 March 2017 16 months after consent |
Screening a site of your own?
Mansfield approves 85% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Littlewood Lane Solar’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Mansfield’s record on solar
Mansfield has decided 13 solar farms and approved 85%, taking a median of 3 months. See every solar farm decision in Mansfield →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 2.5 km |
Solar Photovoltaics · Operational | 3.8 | 2.8 km |
Solar Photovoltaics · Operational | 11.3 | 6.5 km |
Landfill Gas · Operational | 2 | 7.3 km |
Solar Photovoltaics · Operational | 5 | 7.3 km |
Landfill Gas · Operational | 1.2 | 7.4 km |
Wind Onshore · Operational | 15 | 7.9 km |
Landfill Gas · Operational | 3 | 8.1 km |
How big is Littlewood Lane Solar?
Littlewood Lane Solar has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Littlewood Lane Solar?
REPD records the operator as Littlewood Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Littlewood Lane Solar approved and built?
The application was submitted on 18 August 2015. Permission was granted on 18 November 2015, 3 months later. The site became operational on 30 March 2017, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5687.